View Full Version : How is your relationship with Procurement?



PmSG
02-04-2017, 04:40 PM
Procurement Department has this idea that they 'own' the project budget and can sometimes go around the Project Manager. Or, Procurement will negotiate with vendors without including the project manager. Any frustrations or thoughts?

JonMQuigley
02-04-2017, 07:38 PM
I have personally seen a project stalled while an organization's purchasing / procurement department negotiate with the supplier. Meanwhile the project schedule ticks away. Ultimately, everybody still expects the project or demands the project to end on time even though significant portions of the schedule had ticked away with little to no work accomplished by the supplier due to contract negotiations.

PmSG
02-06-2017, 05:06 PM
Fortunately, I reported to a Senior PM early in my career that had several issues with Purchasing / Procurement and warned me. Also, I was offered a position as Procurement Leader (and accepted) to help integrate PM tools into 'buying' and supporting buyers to understand what (& why) project managers needed. That was a great position.

PmSG
02-20-2017, 02:44 PM
Two ground rules I set: (1) Any discussions/proposals for MY project funds involves me. (2) I review every purchase order before it is issued and I initial to confirm my review and agreement; includes alterations to a PO. POs have been issued with out my initials and I protest to the highest level. It is not a case of 'getting my way', it is protecting MY approved project funds.

JonMQuigley
09-28-2019, 12:27 PM
The way you are handling it seems only prudent. It is not about Your Way, it is about making informed decisions. Those signing the PO may not know the PO and the amount of money the project is allowed to spend to keep the business case. Any change request that costs reduces that business case, and if it adds cost to the product may eliminate the ability for the product to return the investment as well. These things are all connected.